Call us now on +44 (0) 1206 752017

New Digestate Pelleting Plant successfully commissioned

digestate pelleting plant

Plant installation and commissioning

Turner Process Equipment in conjunction with Amandus Kahl, have recently designed, supplied and installed a new digestate pelleting plant for a large renewable energy producer in East Anglia.

Process design and equipment supply

The process design and equipment supply commenced at the outlet of the client’s existing raw material dryers through to the flat store for finished pelleted product.

digestate pelleting plant
digestate pelleting plant

The pelleting plant comprises of two Amandus Kahl 37-850 flat die pellet presses rated at 2.2tonne/hour each with a counterflow cooler and pellet sieve.  A BRT Hartner decompactor operates as a buffer hopper prior to the press lines.  A central dust filtration and exhaust system services all machines and handling equipment.

Complete electrical and mechanical installation

The electrical and mechanical installation was included within the Turner Process Equipment supply and installation contract and undertaken by D B Brooks and Brookshaw Stuart respectively.

In production

Despite unavoidable delays due to the Covid-19 pandemic and lockdown restrictions, the site installation, dry commissioning, and wet commissioning have been successfully completed and the digestate pelleting plant is now in full production.

digestate pelleting plant
digestate pelleting plant

To find out more about our design, supply and installation services call us on +44 (0) 1206 752017 or email us.